Adani Green Energy Limited’s ambitious 1,500-megawatt Tarali Pumped Storage Project in Maharashtra’s Satara district has found itself at the center of an intensifying regulatory, environmental, and administrative controversy following disclosures that an affidavit submitted by the company lowered its declared project cost by 99 percent, proportionally shrinking its mandatory wildlife conservation deposit from ₹227 crore to just ₹2.27 crore. Amid mounting scrutiny from central environmental authorities and local wildlife conservationists, both the Maharashtra Pollution Control Board and the state forest department have issued stop-work orders halting excavation and construction activities linked to the hydropower project, while a priority investigation ordered by the Union Ministry of Environment, Forest and Climate Change remains underway.
The latest regulatory blow arrived when the Maharashtra Pollution Control Board issued a formal directive instructing Adani Green Energy Limited to immediately cease excavation and construction work linked to the Tarali hydropower project in Satara district. In its communication, the pollution control board stated that excavation and development work at Sawarghar village had been carried out without obtaining prior permission from the board and without requisite environmental clearance. In response, the company maintained that the activities flagged at Sawarghar represent temporary construction-support facilities rather than permanent components of the pumped storage project, asserting that all permanent project elements hold the necessary statutory clearances. Proposed on the Tarali dam reservoir, the 1,500-megawatt Tarali Pumped Storage Project spans 150.74 hectares of non-forest land across Nivade, Tondoshi, Kalambe, and Jalu villages in Patan taluka of Satara district.
The regulatory scrutiny stems directly from a dramatic disparity between the capital expenditure cited in the project's initial environmental approval and the figure later placed on record before state wildlife officials. In a letter dated February 11, 2025, recommending the grant of prior Environment Clearance for the Tarali Pumped Storage Project, the Union Ministry of Environment, Forest and Climate Change recorded the total estimated cost of the project at ₹5,675 crore. According to officials within the Maharashtra forest department, the proposed site falls within the deemed Eco-Sensitive Zone surrounding the Koyna Wildlife Sanctuary in Satara, which forms a critical ecological part of the Sahyadri Tiger Reserve. Under prevailing conservation norms, private entities establishing infrastructure projects within a deemed Eco-Sensitive Zone can be required to deposit up to 4 percent of the total project cost toward wildlife conservation and habitat protection.
Applying this established regulatory formula, the State Board for Wildlife convened on February 23, 2026, and stipulated fifteen binding conditions for clearing the project, including the mandatory requirement that 4 percent of the project cost be deposited directly into the Sahyadri Tiger Reserve’s bank account. Acting on those conditions, Maharashtra’s Principal Chief Conservator of Forests (Wildlife), M Shrinivas Reddy, addressed a formal letter to Adani Green Energy on March 24, 2026, enumerating all fifteen conditions laid down by the state wildlife board and directing the company to deposit ₹227 crore—representing 4 percent of the ₹5,675 crore project cost—into the Sahyadri Tiger Reserve Conservation Foundation. Reddy also instructed the firm to submit an undertaking confirming compliance with the remaining fourteen conditions so that the proposal could be forwarded to the National Board for Wildlife for final consideration. Reaffirming this financial obligation, the Deputy Director of Koyna Wildlife Sanctuary wrote to the company on May 7, 2026, reiterating that the cost of the project passing through the buffer and deemed eco-sensitive zone stood at ₹5,675 crore and that 4 percent, amounting to ₹227 crore, had to be deposited with the Field Director of the Sahyadri Tiger Reserve.
However, the financial calculations shifted dramatically four months later. On September 8, 2026, Adani Green Energy’s Chief Operating Officer, Naresh Telgu, submitted a notarized affidavit concerning the project cost to the Principal Chief Conservator of Forests in Maharashtra. The sworn document stated that while submitting Part IV of the proposal, the cost of the project had been considered based on analogous estimation, and requested the forest department to consider ₹56.75 crore—exactly one-hundredth of the original ₹5,675 crore valuation—as the project cost. On October 12, Principal Chief Conservator of Forests Reddy informed Adani Green Energy that his office had accepted the revised project cost of ₹56.75 crore, directing the company to immediately remit 1 percent of the revised figure, amounting to ₹56.75 lakh, while paying the remaining 3 percent, or ₹1.7075 crore, following formal approval from the National Board for Wildlife. Adani Green Energy subsequently deposited ₹56.75 lakh into the Sahyadri Tiger Reserve’s bank account.
The 99 percent reduction in declared project cost and the corresponding drop of nearly ₹225 crore in wildlife conservation dues soon drew sharp objections from conservationists. On October 30, Rohan Bhate, Honorary Wildlife Warden of Satara district, lodged formal complaints on both the Prime Minister’s grievance redressal portal and the Maharashtra government’s Aaple Sarkar portal, alleging an incorrect declaration of the project's cost. Taking cognizance of the complaint, the Union Ministry of Environment, Forest and Climate Change wrote to the Maharashtra forest department on November 6, directing state officials to investigate the matter on priority and initiate appropriate action, prompting the state department to launch an inquiry.
Following investigative reports detailing the cost revision on November 13, Adani Green Energy strongly rejected allegations that it had attempted to revise overall project costs downward to evade statutory conservation obligations. Initially, an Adani Group spokesperson noted that all Tarali Pumped Storage Project elements sit within private land ownership across three revenue villages in Patan taluka without involving forest land, adding that pumped storage projects cause no adverse impact on downstream ecology, environment, forests, or wildlife during operations. In a subsequent detailed statement, the company characterized allegations of attempting to diminish statutory dues as completely misleading, explaining that the online application submitted on the forest and wildlife portal was exclusively for site investigation purposes, whereas the State Board for Wildlife had referenced the overall project outlay of ₹5,675 crore. Because site investigation expenses typically account for roughly 1 percent of overall project expenditure, the company stated that it had submitted the ₹56.75 crore figure solely to clarify site investigation and survey costs for that specific online proposal. Furthermore, the spokesperson contended that the Tarali project lies entirely on private, non-forest land located 3.2 kilometers away from the Koyna Wildlife Sanctuary, sits outside the notified buffer zone of the Sahyadri Tiger Reserve, and neither impacts any tiger corridor nor diverts any protected area, reserve forest, or notified eco-sensitive zone.
Despite the company’s clarifications, the Maharashtra forest department moved swiftly on November 13—within hours of the initial disclosures—to order an immediate halt to all ongoing work at the Tarali site. Forest officials noted that construction and excavation had commenced without securing prior approval from the National Board for Wildlife, which the department maintains is legally mandatory because the site falls within the deemed Eco-Sensitive Zone of the Sahyadri Tiger Reserve. Alongside the stop-work directive, the forest department demanded a comprehensive written explanation clarifying under what legal authority work had begun without national wildlife board clearance, while requiring the company to produce all statutory clearance documents, project maps, and official permissions authorizing tree felling at the site. While Adani Green Energy reiterated that it had already secured prior Environmental Clearance in February 2025, obtained Consent to Establish in April, acquired necessary land-use permissions, and submitted its complete proposal to the National Board for Wildlife for consideration, all field work at the Satara project remains suspended pending the outcome of the central and state probes.